PJM 2025/2026 Capacity Base Residual Auction Results

PJM 2025/2026 Capacity Base Residual Auction Results

PJM recently concluded its capacity Base Residual Auction (BRA) for Planning Year (PY) 2025/26.  The resulting prices, compared to previous recent auctions, are significantly higher.  

For PY 2024/25, the RTO capacity price is $28.92/MW-day.  

For PY 2025/26, the RTO capacity price cleared at $269.92/MW-day, a more than nine-fold increase.  

Two delivery zones within the RTO are constrained, leading to even higher capacity prices.  The DOM zone cleared at $444.26/MW-day.  The BGE zone cleared at $466.35/MW-day.    

Why have capacity prices risen so much?  The primary reasons are related to (i) increased peak-load forecasts within PJM, (ii) generation retirements (primarily coal) leading to less generation offered into the auction, and (iii) updated FERC market rules.  

What does this mean?  For a 1-megawatt customer with a 50% load factor, we estimate the following impact:

For customers in the DOM and BGE zones, the increases are higher.  

The graph below provides a historic perspective of RTO capacity prices.  Over the 18 planning years prior to 2025/26, prices averaged $89.03, with a high of $174.29 (2010/11) and a low of $16.46 (2012/13).  

When will future capacity auctions be held?  Here is PJM’s schedule:

If you have questions about how this will affect your electricity bill or how you might manage your energy supply costs, please contact us. 

The Avalon Advantage – Visit our website at www.avalonenergy.us, call us at 888-484-8096, or email us at info@avalonenergy.us.

Evelyn Teel contributed to this article.

Please feel free to share this article.  If you do, please email or post the web link.  Unauthorized copying, retransmission, or republication is prohibited.

Copyright 2024 by Avalon Energy® Services LLC